Safe and Time-Efficient Link Bridge for 12m Coverage

  1. Home
  2. Insights & Case Studies
  3. Safe and Time-Efficient Link Bridge for 12m Coverage

Problem Statement 

The client needed to cover a length of 12-13 meters for their project but faced significant challenges due to the unsafe and time-consuming nature of moving a 12-meter scaffold. They required a solution that would allow them to complete the work efficiently and within a tight timeline. 

Our Solution 

Y Equipment Services provided a link bridge scaffold, enabling the client to cover the entire length in one setup. This solution eliminated the need to shift or move the scaffold, allowing for safe and simultaneous work across the span. 

Pain Points Resolved 

  • Time Efficiency: The solution allowed the client to complete the work in approximately 10-15 days instead of 2 months. 
  • Cost Savings: The client saved around ₹20,000 in manpower costs due to the reduced need for labor. 
  • Safety: The link bridge scaffold provided a safe working environment, eliminating the risks associated with moving a large scaffold. 

The client chose Y Equipment Services because they needed to complete their work within the given timeline and in a safe manner. The solution provided by Y Equipment Services saved the client approximately 30 days and ₹20,000 in manpower costs, making it an efficient and cost-effective choice. 